More EVs, Fewer Plugs: How Permit Delays Slow Down Charger Growth
Charging companies say installing stations is fast and easy, but permit approvals can sometimes take more than a year.

Suvrat Kothari 
By: Suvrat Kothari
Jun 11, 2024 at 10:00am ET
Add InsideEVs as a preferred source in Google
- (https://twitter.com/intent/tweet?url=https%3A%2F%2Finsideevs.com%2Fnews%2F722801%2Fcharger-permitting-delays-slow-rollout%2F&text=More%20EVs%2C%20Fewer%20Plugs%3A%20How%20Permit%20Delays%20Slow%20Down%20Charger%20Growth&via=InsideEVs)
- copy
Share
Comment
If you drive an electric car, the chances of encountering a traffic jam at charging stations before finding a spot to plug in are higher today than ever. That's especially true in large, congested cities like New York or Chicago. This is because the pace of EV sales has far outpaced the installation of public chargers.
In 2016, there were seven EVs for every public charging point in the U.S. With a surge in EV sales in recent years, that number has increased to 20 EVs per public charger, according to the U.S. Department of Energy's Alternative Fuels Data Center.
Many charging companies are now saying that one reason for this skewed ratio is the lengthy process involved in acquiring permits and getting utility companies on board.
Get Fully Charged
Chargers and EVs: The "chicken and egg" scenario
Experts and ordinary drivers alike believe EVs won't really take off until communities everywhere have an abundance of public charging. But how do we ensure both of those things happen in lockstep? The growth of the charging business has been held up by many factors, including how much the installation process varies from place to place.
Even though charging infrastructure has expanded over the past few years, recent roadblocks have slowed progress. Tesla, for example, slowed the expansion of Superchargers last month amid global layoffs, which also included the Supercharger team itself. (Some of those dismissed workers have since been rehired at Tesla, while many found roles at other companies.)
When it comes to federal programs, the rollout has been embarrassingly slow. Out of the 500,000 chargers planned to be funded under the Biden Administration's National Electric Vehicle Infrastructure program, which launched in 2022, only eight stations are open across six states.
Under that program, states apply for funding and then private companies make bids to install chargers. However, the charging companies who receive NEVI funds must comply with a complex web of local regulations, work with utility companies and get required permits—a process that can vary wildly from community to community.
These delays have ripple effects that a rapidly warming planet can ill afford. Not only does it cause inconvenience to EV drivers, with long lines and overburdened existing dispensers, but also hampers the broader adoption of battery-powered vehicles. (It's worth noting that the ratio of EVs to chargers varies regionally and leaves out residential chargers. The use-case of specific stations also varies, including uptime, reliability, charging speeds, etc.)

Long Permitting Process
“We often need to navigate local, state and other federal permitting rules to build our charging stations,” Andrew Cornelia, the president and CEO of Mercedes-Benz High Power Charging, told InsideEVs. “And one of the challenges is that these requirements vary by jurisdiction and they slow down the development cycle."
Building charging stations typically involves multiple steps. First, charging companies must select accessible locations and secure agreements with site hosts. These hosts often include retailers such as Target or Walmart, which have large parking lots along busy traffic corridors.
Next, collaboration with utility companies is required to route electricity to the site. This is followed by the design and construction of the charging station. The main roadblock arises during the permit acquisition process from local jurisdictions, which can take anywhere from a few weeks to over a year.
Get the best news, reviews, columns, and more delivered straight to your inbox.
back
Subscribe For more info, read our Privacy Policy & Terms of Use.
“Once we know that we're going to get power to the site, building the site is a quick process,” said Anthony Lambkin, the vice president of operations at Electrify America. “[Building a charging station] usually takes between four to six weeks, but can vary depending on how big the site is, or any other complications related to construction.”
But getting to that point can take a while. Charging companies says there are proven examples of how to streamline the process.
“The more actionable idea is to have states do something that California did, have processes that allow streamlined permitting,” Lambkin added. In 2015, California enacted a law labeled AB 1236 to begin streamlining the permitting process for charging stations.
The bill imposes time restrictions on local jurisdictions to accept applications and approve them. It mandates that an application for a site with 1-25 dispensers has to be accepted within five business days and approved within 20 business days. Approvals can only be delayed if the applications are inconsistent with the permitting checklist or pose health or safety risks.
As a result, California is now the most EV-friendly state in the U.S. In addition to having the most EV registrations, it also has nearly 53,000 non-residential public charging ports, more than the next five states combined, according to Department of Energy data. If you include public Level 2 chargers, DC fast chargers and shared private chargers, that number tops 105,000.
“We need to demystify charging permitting at a state level and then require towns and cities [to make permitting process] easily accessible,” Lambkin said. “The steps involved should be public. Publish it on a website and have an electronic submittal program,” he added.
Having clear information available on public platforms would help stakeholders understand the process and expedite the approvals. “This way, I know the timing involved in each step and I know that within three to four weeks, I'm going to have my approved permit,” Lambkin added.
Delays With Utility Interconnections
Determining the electrical capacity and infrastructure necessary to support the charging station also takes a long time. This includes working with local utility companies to evaluate the existing electrical supply and identifying any necessary upgrades—a crucial step for the reliable and efficient operation of charging stations.
A stable connection ensures enough power supply. But if a particular site cannot get supply lines in for some reason, utility companies should notify charging companies in advance and provide a timeline as to when power would be available. This helps with planning and reallocation of resources towards sites where installation is viable, Lambkin said.
“Right now we're seeing a pretty cumbersome process in terms of utility interconnection,” Cornelia said. “This spans everything from studies to the actual transformer supply which can take months. It can take years even,” he added.

According to Cornelia, “proactive planning” is needed to ensure that charging stations can connect to the grid at scale without delay. By that, he means actively communicating and coordinating with people within the utility companies to ensure that they plan grid capacity ahead of time.
Mercedes-Benz has been more proactive than other automakers at taking this on. Cornelia's division, Mercedes-Benz High Power Charging, exists to try and take out the many uncomfortable headaches—like charging in remote, dirty and potentially unsafe locations—that no owner of a $100,000 luxury car wants to deal with.
It opened its first 400-kilowatt charging hub at Mercedes-Benz USA headquarters in Sandy Springs, Georgia, last November. Since then, it has installed another 12 locations in the Southeast with convenience store giant Buc-ee’s. It plans to expand much further.
Cornelia said Mercedes-Benz HPC worked closely with Southern Company, one of the largest utility companies in the U.S., to meet an “ambitious timeline” to launch its first charging hub.
“We built a relationship with the Southern Company, where we initially saw transformer lead times of about 90 weeks. Through proactive collaboration, we were able to bring that down to 12 weeks,” Cornelia said.
“It’s literally knowing the right person within these utilities. Having the right people who bring the expertise and the relationships to the table is critical to navigating the environment we live in.”
It also comes down to whether a state or individual utility is progressive and forward-thinking or not. “There’s always a natural lead time to developing critical infrastructure like EV charging,” Cornelia said. “What makes the difference between some providers and others is a clear commitment and a long-term vision of how to manage that.”
Affordable models are expected to spur the sales of EVs during the remainder of the decade. A ton of charging projects have also been announced recently, including the expansion of Electrify America and Mercedes-Benz HPC networks and the new Tesla-rivaling Ionna network from a consortium of seven automakers among others.
What do you think?
View
Comments
If EV sales and the charging networks have to grow with synergy, having a streamlined approval mechanism for chargers in every state is a necessity. Fifty years from now, we don't want to say that we missed the window for combatting climate change purely because we couldn't get the permits.
Contact the author: suvrat.kothari@insideevs.com
More EV News
Tesla Model Y's 'Juniper' Update Won't Happen This Year, Musk Says
Hyundai And Kia Now Own 11% Of America's EV Sales Through May 2024
Costco May Save General Motors' EV Buyers From Dealer Headaches
Tesla Faces A $56 Billion Question. Does Elon Musk Have The Votes?
We want your opinion!
What would you like to see on Insideevs.com?
Take our 3 minute survey.
- The InsideEVs team
Share this Story
- (https://twitter.com/intent/tweet?url=https%3A%2F%2Finsideevs.com%2Fnews%2F722801%2Fcharger-permitting-delays-slow-rollout%2F&text=More%20EVs%2C%20Fewer%20Plugs%3A%20How%20Permit%20Delays%20Slow%20Down%20Charger%20Growth&via=InsideEVs)
- copy
GO TO COMMENTS
(
)
Got a tip for us? Email: tips@insideevs.com
View all comments ( )
Trending

Kia EV3 Lease Deals Are Here, And It’s Cheaper Than The Chevy Bolt And Nissan Leaf

I Let Android Auto Plan My EV Roadtrip. Here’s How It Worked

This Chevy Bolt Has 470,000 Miles. Here’s How Much A New Battery Was

Here's What It's Like To Take Delivery Of A Rivian R2
latest articles
- Waymo Plans To Have 20,000 Cars By The End Of 2027 Oct 20 - News -
- The Boring Company Uses Tesla Model 3 Sleds To Shuttle Shipping Containers Through Its Tunnels Oct 20 - News -
- How Much Range Do EVs Lose When Parked? (And How to Stop It) Oct 20 - EV 101 -
- This Chinese EV Is Now Made In Europe. More Are Coming Oct 20 - News -
- GM Is Closing Its Detroit EV Battery Plant Oct 20 - Industry -
- The 2027 Lexus NX Plug-In Hybrid Gets A Bigger Battery And Fast Charging Oct 20 - Official -
- Kia EV3 Lease Deals Are Here, And It’s Cheaper Than The Chevy Bolt And Nissan Leaf Oct 20 - Pricing -
RECOMMENDED FOR YOU

Used EVs Hit A Record Share Of Overall Used Car Sales In September

This Chinese EV Is Now Made In Europe. More Are Coming

The Roadster Will Have Tesla’s Most Advanced Battery Pack Yet

GM Is Closing Its Detroit EV Battery Plant

Tesla 'Cannot Guarantee' Your Roadster Pre-Order Will Ever Be Delivered

The 2027 Lexus NX Plug-In Hybrid Gets A Bigger Battery And Fast Charging

Tesla Just Revealed The Roadster With A Truly Insane Demo. Here's What You Need To Know